The Details
Personal
Metros
Días
WORK DIAGNOSIS
Joints for installing on the bridge over the Puerto Inca River a new bridge, which has an asphaltic folder 9cm thick.
SOLUTION
Carry out the installation of joints, CAUCHOS VIKINGO, installed JCV-250 joints for approximately 38 linear meters, which included direct installation.
Start date: August 28, 2014
Completion date: August 1, 2014.
Working time: 5 days
BENEFIT
The joints offered by CAUCHOS VIKINGO are made with Neoprene; Allowing large-scale movements between two parts of the structure; Is resistant to extreme environmental conditions and are designed for heavy traffic, in addition to helping to keep the asphalt layer in good condition, avoiding deterioration due to conditions already mentioned.
The Builder benefits by purchasing high quality Ecuadorian products with international competitiveness, which prevents them from importing and helps to reduce costs.
HUMAN TALENT
The personnel required for this work consists of the following list of highly qualified personnel:
Work supervisor: 1
Work Assistants: 4
Total staff required: 5 people