WORK DIAGNOSIS
Proyecto Recreo Shopping Center in the City of Quito, we have a structural space of 5 cm for the adaptation of Local Payless Shoes.
SOLUTION
Perform the installation of JAV-50 joints CAUCHOS VIKINGO, form of direct installation .
Working time: 5 days
BENEFIT
The joints offered by CAUCHOS VIKINGO are made with steel; Allowing large-scale movements between two parts of the structure; Is resistant to extreme environmental conditions and are designed for heavy traffic, in addition to helping to keep the asphalt layer in good condition, avoiding deterioration due to conditions already mentioned.
The Builder benefits by purchasing high quality Ecuadorian products with international competitiveness, which prevents them from importing and helps to reduce costs.
HUMAN TALENT
The personnel required for this work consists of the following list of highly qualified personnel:
Work supervisor: 1
Work Assistants: 2
Total staff required: 3 people